MANAGEMENT CONSIDERATIONS
RESPONSIBILITY
works will
during The CEMP is to include appropriate noise mitigation Contractor.
propriate measures including:
•
•
•
•
•
All machinery on site to comply with maximum
noise limits under POEO Act and associated
guidelines.
Turning off plant, machinery, and vehicles when
not in use.
Notification of commencement to neighbours or
relevant parties, prior to construction work.
No construction outside of normal construction
hours unless approved by Council.
When notifying neighbours or relevant parties impacted
by the works, contact details should be provided in case
the public wish to ask questions or make a complaint.
bed areas Construction contractor to include rehabilitation of
gressively exposed surfaces that have resulted from the works Contractor.
(e.g., turfing) that may cause other issues in the
future (e.g., erosion and sedimentation).
ter: Soils
Landscaping is to be implemented in accordance with
ne; and the approved plans.
deline for
Using
dures for Prior to the relevant works, a Construction Traffic Contractor.
during Management Plan is to be prepared (separately or
edestrian part of the CEMP) to ensure minimal disturbance to
the local road and network and pedestrian/cycle
movements.